EPC project management  

For equipment installation projects, trial runs shall be organized. The content of the test run shall be consistent with the installation scope contracted by the contractor.


(1) single no-load test


If the equipment installation project has the condition of single machine no-load test, the contractor shall organize the test run. Only when the single test run meets the specified requirements, can the combined test be carried out. The contractor shall notify the engineer in writing 48 hours prior to the commissioning. The notice includes the test content, time and place. The contractor keeps test records and the owner provides necessary conditions for the test. The engineer signs the test record after passing the test.


(2) linkage no-load test


If the equipment installation project has the condition of no-load linkage test, the owner shall organize the test and notify the contractor in writing 48 hours before the test. The notice includes the test content, time, place and requirements for the contractor, who shall prepare the work and test record as required. Both parties shall sign the test record after passing the test.


(3) commissioning


The owner shall be fully responsible for the commissioning after the acceptance of the project. If the employer requires the contractor to cooperate or carry out the work before the completion and acceptance of the project, it shall obtain the consent of the contractor and sign a supplementary agreement.

Link:
北京君利安工程技术有限公司
北京君利安工程技术有限公司
Official WeChat
北京君利安工程技术有限公司
Mobile cloud website
Contant us
A8-1325, no.1 yuehua street, gongchen street, fangshan district, Beijing
Web site:www.junlean.com
Phone:400-606-8929
Copyright ©2019 - 2021 Beijing Junlean Engineering Technology Co. Ltd.
Rhino cloud enterprise cloud services